HMGMA BUILDING PAINT SHOP GC PROJECT
Client
Hyundai
Year
JAN 2023 – IN PROGRESS
Location
ELLABELL, GA
Linked white arrow
HMGMA BUILDING PAINT SHOP GC PROJECT
SYSCON understands what it takes to see a major construction project to completion. One of the most vital aspects of any successful project is expert planning and preconstruction. SYSCON understands what it takes to see a major construction project to completion. One of the most vital aspects of any successful project is expert planning and preconstruction. SYSCON understands what it takes to see a major construction project to completion. One of the most vital aspects of any successful project is expert planning and preconstruction.
Project Scope Details
DESIGN
HAEAHN
GENERAL CONTRACTOR
HYUNDAI ENG AMERICA, INC.
MAIN SUBCONRTRACTOR
SYSCON
LOT AREA
29.56 ACRES
CONSTRUCTION AREA

595,297 SF

Floors

MAIN PLANT

BUILDING STRUCTURES

S/STRUCTURES

WALL PANEL (3”)

TPO (3”) ROOFING

MAJOR ACTIVITIES

ARCH. GENERAL CONTRACTOR

S/STRUCTURE: 16,000 TONS

CONCRETE: 48,000 CYD, WALL PANEL, ROOFING, SIPHONIC

Project Scope Details
GENERAL CONTRACTOR
HYUNDAI ENG AMERICA, INC.
MAIN SUBCONTRACTOR
SYSCON
LOT AREA
29.56 ACRES
CONSTRUCTION AREA
595,297 SQ FT
Project Scope Details
LOT AREA
This is some text inside of a div block.
CONSTRUCTION AREA
This is some text inside of a div block.
ELEVATION
This is some text inside of a div block.
BUILDING STRUCTURES
This is some text inside of a div block.
MAJOR ACTIVITES
This is some text inside of a div block.
DESIGN
This is some text inside of a div block.
FLOORS
MAIN PLANT
BUILDING STRUCTURES
S/STRUCTURES+WALL PANEL (3”) + TPO (3”) ROOFING
MAJOR ACTIVITES
ARCH. GENERAL CONTRACTOR, S/STRUCTURE: 16,000 TONS, CONCRETE: 48,000 CYD, WALL PANEL, ROOFING, SIPHONIC